Task 1 Project Management (milestone)
- Additional estimation integration improvements in PR #328 based on feedback from SEMCOG, SFCTA, and Jeff Newman
Task 2 Strategic Planning (milestone)
- Working through comments on the draft strategic development and contribution plan
- Any others?
- We're planning to discuss August 20th
Task 10 Support for Three Zone Systems and TVPB (milestone)
- Revised more robust TM2 test example with Lisa/MTC
- @Lisa working on data prep; I'm working on expression revisions