As a team a want a overview of minor milstones in MVP2 and the dependencies #1659
Closed
29 tasks done
Labels
kind/analysis
Used when an issue needs to be analysed before it becomes a user story.
Milestone
Description
In MVP2 we have different milestones. This issues List the minor milestones with a description of goals and all task/epic that needs to be complete to fulfill them.
Deploy app container to org cluster - Week 20
In this milestone it is possible to deploy a app container build in Altinn Studio to Altinn Apps org cluster
Possible to navigate to app container with a logged in user - Week 23 (Completed Week 28)
In this milestone a user can log in to AT21 and then use a direct link to a app Container and the container will know which user that accessed the start service page
- [ ] Minimum start service pageTime prioritised for actual instantiation- [ ] PartyList mockedTime prioritised for actual instantiationAble to instantiate a instance of a App - Week 24
In this milestone a user can instansiate app (create a default data instance)
Able to design a pilot app with all needed components - Week 24
In this milestone the UI-designer has all the components the pilot services need
Org can instantiate app - Week 25
Able to complete process in Pilot App and submit final data in end of process - Week 25
After this milestone a user can complete filling in the form with the needed data
~~- [ ] Complete process handling for MVP workflow Implement solution for (flexible) process #1368
Service Owner Can download data from storage component - Week 26
This milestone makes it possible for service owners to download the data.
~~- [ ] Authentication of agency systems established in Authentication component
Messagebox integration with Altinn Platform - Week 26
In this scenario the instances in Altinn Platform is listed in Messagebox/archive