The project will follow this process:

  • Project team formation
  • Project proposal
  • Project sprint 1 (Features + Setup)
  • Project sprint 2 (Proof-of-Concept)
    • Revised requirements and specification
    • Design and planning
    • Working code up to project sprint 2
  • Project sprint 3 (Feature Development)
    • Revised requirements and specification
    • Revised design and planning
    • Working code up to project sprint 3
  • Project sprint 4 (Exception Handling + Testing)
    • Revised requirements and specification
    • Revised design and planning
    • Working code up to project sprint 4
  • Project sprint 5 (Deployment + Optimization)
    • Revised requirements and specification
    • Revised design and planning
    • Working code up to project sprint 5
  • Project sprint 6 (Wrap Up!)
    • Revised requirements and specification
    • Revised design and planning
    • Working code up to project sprint 6
  • Final demo poster session & final report

Note : Every document for each milestones must be written in English!

Sprint Instructions

Project Timeline

Start End TA meeting
Sprint 1 Sep. 23 (Mon) Oct. 5 (Sat), 6pm(report due) TH/F
Sprint 2 Oct. 7 (Mon) Oct. 20 (Sat), 6pm(report due) TH/F
Project progress presentation Oct. 24 practice session (Tentative)
Sprint 3 Oct. 21 (Mon) Nov. 2 (Sat), 6pm(report due) TH/F
Sprint 4 Nov. 4 (Mon) Nov. 16 (Sat), 6pm(report due) TH/F
Sprint 5 Nov. 18 (Mon) Nov. 30 (Sat), 6pm(report due) TH/F
Sprint 6 Dec. 2 (Mon) Dec. 14 (Sat), 6pm report TH/F
Final poster Dec. 16 (Mon) 5pm - 9pm
Final report Dec. 18 (Wed) 6pm