This page shows the current proposals for migrating instruments from SECI to IBEX. Please note that the information on this page is subject to change. Migration of individual instruments is by agreement and in consultation with the relevant instrument scientists.

Migration of instruments will, in general, take place during shutdown periods (unless there is an opportunity to do so during cycle). Preparation for migration will take place in the cycle preceding the indicated shutdown in the table below.

Migration Schedule

Duration of shutdown periods is in days.

Cycle Start Finish Duration Instruments to be migrated
2019/04 11-Feb-20 27-Mar-20
Shutdown 28-Mar-20 27-Apr-20 30 POLREF, MuSR
2020/01 28-Apr-20 05-Jun-20
Shutdown 06-Jun-20 07-Sep-20 93 INTER, SANS2D
2020/02 08-Sep-20 23-Oct-20
Shutdown 24-Oct-20 09-Nov-20 16 SXD, HIFI
2020/03 10-Nov-20 17-Dec-20
Long Shutdown 18-Dec-20 06-Sep-21 262 WISH, PEARL, ChipIR,
ARGUS, CHRONUS, OFFSPEC