Instrument Migration Plan
kjwoodsISIS edited this page Nov 30, 2018
·
26 revisions
This page shows the current proposals for migrating instruments from SECI to IBEX. Please note that the information on this page is subject to change. Migration of individual instruments is by agreement and in consultation with the relevant instrument scientists.
Migration of instruments will, in general, take place during shutdown periods (unless there is an opportunity to do so during cycle). Preparation for migration will take place in the cycle preceding the indicated shutdown in the table below.
Please note: dates after 31-December-2018 are not yet confirmed (the accelerator schedule has not yet been published beyond this date).
Duration of shutdown periods is in days.
Cycle | Start | Finish | Duration | Instruments to be migrated |
---|---|---|---|---|
58 | ||||
16 |
|
|||
2018/03 | 13-Nov-18 | 18-Dec-18 | ||
Shutdown | 19-Dec-18 | 04-Feb-19 | 47 | LOQ, SURF, LET, MARI |
2018/04 | 05-Feb-19 | 29-Mar-19 | ||
Shutdown | 30-Mar-19 | 03-Jun-19 | 65 | INTER, SANS2D, NIMROD, EMU, PEARL |
2019/01 | 04-Jun-19 | 19-Jul-19 | ||
Shutdown | 20-Jul-19 | 09-Sep-19 | 51 | OFFSPEC, POLREF, WISH, SXD |
2019/02 | 10-Sep-19 | 25-Oct-19 | ||
Shutdown | 26-Oct-19 | 11-Nov-19 | 16 | ARGUS, CHRONUS |
2019/03 | 12-Nov-19 | 20-Dec-19 | ||
Shutdown | 21-Dec-19 | 10-Feb-20 | 51 | ChipIR, MuSR, HIFI |
2019/04 | 11-Feb-20 | 27-Mar-20 |