Instrument Migration Plan

kjwoodsISIS edited this page Apr 12, 2017 · 26 revisions

Instrument Migration Plan

This page is under construction

This page shows the current plan for migrating instruments from SECI to IBEX. Please note that the information on this page is subject to change.

Migration Schedule

Please note: dates after 31-March-2018 are approximate (the accelerator schedule has not yet been published beyond this date).
Duration of shutdown periods is in days.

Cycle Start Finish Duration Instruments to be migrated
2016/04 15-Nov-16 16-Dec-16
Shutdown 17-Dec-16 13-Feb-17 58 VESUVIO, ZOOM, ALF
2016/05 14-Feb-17 31-Mar-17
Shutdown 01-Apr-17 01-May-17 30 POLARIS, HRPD
2017/01 02-May-17 02-Jun-17
Shutdown 03-Jun-17 18-Sep-17 81 MERLIN, ENGIN-X, GEM, EMMA, NIMROD, SANDALS, CHIPIR
2017/03 19-Sep-17 27-Oct-17
Shutdown 28-Oct-17 13-Nov-17 16 SXD, INES
2017/04 14-Nov-17 20-Dec-17
Shutdown 21-Dec-17 12-Feb-18 53 MAPS, MARI, PEARL
2017/05 13-Feb-18 30-Mar-18
Shutdown 31-Mar-18 30-Apr-18 30
2018/01 01-May-18 01-Jun-18
Shutdown 02-Jun-18 09-Jul-18 37
2018/02 10-Jul-18 10-Aug-18
Shutdown 11-Aug-18 17-Sep-18 37
2018/03 18-Sep-18 26-Oct-18
Shutdown 27-Oct-18 12-Nov-18 16
2018/04 13-Nov-18 21-Dec-18
Shutdown 22-Dec-18 11-Feb-19 51
2018/05 12-Feb-19 29-Mar-19
Shutdown 30-Mar-19 30-Apr-19 31

Instruments yet to be Scheduled

The migration of the following instruments is yet to be scheduled: CRISP, EMU, HIFI, INES, INTER, LET, LOQ, MARI, MERLIN, MUSR, NIMROD, OFFSPEC, OSIRIS, PEARL, POLREF, SANDALS, SANS2D, SURF, SXD, TOSCA, WISH.