Instrument Migration Plan

kjwoodsISIS edited this page Nov 28, 2018 · 26 revisions

Instrument Migration Plan

This page shows the current proposals for migrating instruments from SECI to IBEX. Please note that the information on this page is subject to change. Migration of individual instruments is by agreement and in consultation with the relevant instrument scientists.

Migration of instruments will, in general, take place during shutdown periods (unless there is an opportunity to do so during cycle). Preparation for migration will take place in the cycle preceding the indicated shutdown in the table below.

Migration Schedule

Please note: dates after 31-December-2018 are not yet confirmed (the accelerator schedule has not yet been published beyond this date).
Duration of shutdown periods is in days.

Cycle Start Finish Duration Instruments to be migrated
2018/01 05-Jun-18 13-Jul-18
Shutdown 14-Jul-18 10-Sep-18 58 CRISP
2018/02 11-Sep-18 26-Oct-18
Shutdown 27-Oct-18 12-Nov-18 16 INES, TOSCA, OSIRIS
​2018/03 13-Nov-18 18-Dec-18
Shutdown 19-Dec-18 04-Feb-19 47 LOQ, SURF, LET, MARI
2018/04 05-Feb-19 29-Mar-19
Shutdown 30-Mar-19 03-Jun-19 65 INTER, SANS2D, NIMROD, MUSR, PEARL
2019/01 04-Jun-19 19-Jul-19
Shutdown 20-Jul-19 09-Sep-19 51 OFFSPEC, POLREF, WISH, SXD
2019/02 10-Sep-19 25-Oct-19
Shutdown 26-Oct-19 11-Nov-19 16 ARGUS, CHRONUS
2019/03 12-Nov-19 20-Dec-19
Shutdown 21-Dec-19 10-Feb-20 51 ChipIR, EMU, HIFI
2019/04 11-Feb-20 27-Mar-20