Instrument Migration Plan

kjwoodsISIS edited this page Dec 5, 2016 · 26 revisions

Instrument Migration Plan

This page is under construction

This page shows the current plan for migrating instruments from SECI to IBEX. Please note that the information on this page is subject to change.

Migration Schedule

Please note: dates after 31-March-2018 are approximate (the accelerator schedule has not yet been published). Duration of shutdown periods is in days.

Phase Cycle Start Finish Duration Instruments to be migrated
1 2016/04 15-Nov-16 16-Dec-16
1 Shutdown 17-Dec-16 13-Feb-17 58 VESUVIO, ZOOM, ALF
1 2016/05 14-Feb-17 31-Mar-17
2 Shutdown 01-Apr-17 01-May-17 30
2 2017/01 02-May-17 02-Jun-17
2 Shutdown 03-Jun-17 10-Jul-17 37
2 2017/02 11-Jul-17 04-Aug-17
3 Shutdown 05-Aug-17 18-Sep-17 44
3 2017/03 19-Sep-17 27-Oct-17
3 Shutdown 28-Oct-17 13-Nov-17 16
3 2017/04 14-Nov-17 20-Dec-17
3 Shutdown 21-Dec-17 12-Feb-18 53
3 2017/05 13-Feb-18 30-Mar-18
4 Shutdown 31-Mar-18 30-Apr-18 30
4 2018/01 01-May-18 01-Jun-18
4 Shutdown 02-Jun-18 09-Jul-18 37
4 2018/02 10-Jul-18 10-Aug-18
5 Shutdown 11-Aug-18 17-Sep-18 37
5 2018/03 18-Sep-18 26-Oct-18
5 Shutdown 27-Oct-18 12-Nov-18 16
5 2018/04 13-Nov-18 21-Dec-18
5 Shutdown 22-Dec-18 11-Feb-19 51
5 2018/05 12-Feb-19 29-Mar-19
6 Shutdown 30-Mar-19 30-Apr-19 31
  |         |           |           |    | |