Project cadence & duration

The project is expected to take 40 hours per participant, spread over 8 weeks.

Each week, the team of 4 developers will split into 2 pairs of 2 developers each. Each pair will take on a story or task from the issues list to work on together that week.

Pairings will go as follows:

Week 1, July 10 - 16

  1. Dani & Sam
  2. Tatyana & Yolanda

Week 2, July 17 - 23

  1. Yolanda & Dani
  2. Sam & Tatyana

Week 3, July 24 - 30

  1. Tatyana & Dani
  2. Sam & Yolanda

Week 4, July 31 - August 6

  1. Dani & Sam
  2. Tatyana & Yolanda

Week 5, August 7 - 13

  1. Yolanda & Dani
  2. Sam & Tatyana

Week 6, August 14 - 20

  1. Tatyana & Dani
  2. Sam & Yolanda

Week 7, August 21 - 27

  1. Dani & Sam
  2. Tatyana & Yolanda

Week 8, August 28 - September 3

  1. Yolanda & Dani
  2. Sam & Tatyana